October timelines and work plan

Posted by Mohammed Conteh

Posted 21 Sept 2024

We plan to start the field operations at the end of the month. The full work plan is attached.

Date Activity
30th Sep - 1st Oct Identification of qualifying farms
7th Oct - 11th Oct Survey of Needs Assessment
14th Oct - 16th Oct Consultative meetings with community stakeholders
17th Oct - 21st Oct Farm Registration
22nd Oct Engaging farmers on land preparation
22nd Oct - 25th Oct Distribution of seeds
28th Oct - 31st Oct Preparation of first-month report